(3) Business Unit C has included IR&D and B&P costs in its G&A expense pool. Unit C has used a cost of sales base to allocate its G&A expense pool. As of January 1, 1978 (assumed for purposes of this illustration), the date on which Unit C must first allocate its G&A expense pool in accordance with the requirements of this Standard, Unit C has among its final cost objectives several cost reimbursement contracts and fixed price contracts subject to the CAS clause (referred to as the preexisting contracts). If Unit C chooses to use the transition method in 9904.410-50(e):
- (i) Unit C shall allocate IR&D and B&P costs during the transition period (from January 1, 1978, to and including the cost accounting period during which the preexisting contracts are completed), to the preexisting contracts as part of its G&A expense pool using a cost of sales base pursuant to 9904.410-50(e) and appendix A to 9904.410.
- (ii) During the transition period such costs, as part of the G&A expense pool, shall be allocated to new cost reimbursement contracts and new fixed price contracts subject to the CAS clause using a cost input base as required by 9904.410-50 (d) and (e) and appendix A to 9904.410.
- (iii) Beginning with the cost accounting period after the transition period the IR&D and B&P costs, as part of the G&A expense pool, shall be allocated to all final cost objectives using a cost input base as required by 9904.410-50(d). If Unit C chooses not to use the transition method in 9904.410-50(e), the contractual provision requiring appropriate equitable adjustment of the prices of affected prime contracts and subcontracts will be implemented.