48 C.F.R. § 970.1504-107
(a) There are five classification factors. They are tied to facility/task categories. Step 4 in calculating the maximum total available fee amount for the one-year period (see 970.1504-104(b)(4)) is to multiply the fee subtotal in step 3 for each type of effort by the appropriate classification factor. The classification factors and their corresponding facility/task categories are:
| Facility/task category | Classification factor |
|---|---|
| A | 3.0 |
| B | 2.5 |
| C | 2.0 |
| D | 1.5 |
| E | 1.0 |
(b) The Contracting Officer shall select the Facility/Task Category after considering the following:
(1) Facility/Task Category A. The main focus of effort performed is related to—
(2) Facility/Task Category B. The main focus of effort performed is related to—
(3) Facility/Task Category C. The main focus of effort performed is related to—