(c) Upon receipt of the contractor's notice under paragraph (c) of the clause at 1052.232-90, Limitation of Government's Obligation, the contracting officer shall promptly provide written notice to the contractor that the Government is—
- (i) Obligating additional funds for continued performance and increasing the Government's limitation of obligation in a specified amount;
- (ii) Obligating the full amount of funds needed;
- (iii) Terminating for convenience, as applicable, the affected line items or contract; or
(iv) Considering whether to allot additional funds; and
- (A) The contractor is entitled by the contract terms to stop work when the Government's limitation of obligation is reached; and
- (B) Any costs expended beyond the Government's limitation of obligation are at the contractor's risk.