- (a) The contracting officer will inform the successful offeror of significant matters of interest, including—(1) statutory matters such as labor standards (subpart 22.4), and subcontracting plan requirements (subpart 19.7); and (2) other matters of significant interest, including who has authority to decide matters such as contractual, administrative (e.g., security, safety, and fire and environmental protection), and construction responsibilities.
- (b) As appropriate, the contracting officer may issue an explanatory letter or conduct a preconstruction conference.
(c) If a preconstruction conference is to be held, the contracting officer shall—
- (1) Conduct the conference prior to the start of construction at the work site;
- (2) Notify the successful offeror of the date, time, and location of the conference (see 36.522); and
- (3) Inform the successful offeror of the proposed agenda and any need for attendance by subcontractors.
[59 FR 67049, Dec. 28, 1994]