(a) The contracting officer shall issue a final decision as required by 33.211 if—
- (1) The contracting officer and the contractor are unable to reach agreement on the existence or amount of a debt in a timely manner;
- (2) The contractor fails to liquidate a debt previously demanded by the contracting officer within the timeline specified in the demand for payment unless the amounts were not repaid because the contractor has requested an installment payment agreement; or
- (3) The contractor requests a deferment of collection on a debt previously demanded by the contracting officer (see 32.607-2).