(a) General. Cost of money—
- (1) Is an imputed cost that is not a form of interest on borrowings (see 31.205-20);
- (2) Is an “incurred cost” for cost-reimbursement purposes under applicable cost-reimbursement contracts and for progress payment purposes under fixed-price contracts; and
(3) Refers to—
- (i) Facilities capital cost of money (48 CFR 9904.414); and
- (ii) Cost of money as an element of the cost of capital assets under construction (48 CFR 9904.417).
(b) Cost of money is allowable, provided—
- (1) It is measured, assigned, and allocated to contracts in accordance with 48 CFR 9904.414 or measured and added to the cost of capital assets under construction in accordance with 48 CFR 9904.417, as applicable;
- (2) The requirements of 31.205-52, which limit the allowability of cost of money, are followed; and
- (3) The estimated facilities capital cost of money is specifically identified and proposed in cost proposals relating to the contract under which the cost is to be claimed.
- (c) Actual interest cost in lieu of the calculated imputed cost of money is unallowable.
[68 FR 28091, May 22, 2003]