(a) The following plans must be submitted to the Coast Guard for approval in accordance with §§ 50.20-5 and 50.20-10 of this chapter:
- (1) A general arrangement plan of control and monitoring equipment, control locations, and the systems served.
- (2) Control and monitoring console, panel, and enclosure layouts.
- (3) Schematic or logic diagrams including functional relationships, a written description of operation, and sequences of events for all modes of operation.
- (4) A description of control or monitoring system connections to non-vital systems.
- (5) A description of programmable features.
- (6) A description of built-in test features and diagnostics.
- (7) Design Verification and Periodic Safety test procedures described in subpart 61.40 of this subchapter.
- (8) Control system normal and emergency operating instructions.
- (b) [Reserved]
[CGD 81-030, 53 FR 17838, May 18, 1988, as amended by USCG-2014-0688, 79 FR 58280, Sept. 29, 2014]