- (a) Tubes, pipe, and nipples must be attached to sheets, heads, headers, and fittings as indicated in PWT-11 of Section I of the ASME BPVC (incorporated by reference; see § 52.01-1) except as noted otherwise in this section.
- (b) (Replaces PWT-9.2 and PWT-11.3.) Threaded boiler tubes are not permitted as described by PWT-9.2 and PWT-11.3 of Section I of the ASME BPVC.
- (c) In welded wall construction employing stub and welded wall panels that are field welded, 10 percent of the field welds must be checked using any acceptable nondestructive test method.
- (d) Nondestructive testing of the butt-welded joints must meet the requirements of § 56.95-10 of this subchapter.
[CGFR 68-82, 33 FR 18815, Dec. 18, 1968, as amended by CGFR 69-127, 35 FR 9976, June 17, 1970; CGD 81-79, 50 FR 9434, Mar. 8, 1985; USCG-2003-16630, 73 FR 65161, Oct. 31, 2008]