(a) If initially or after an environmental assessment has been completed, it is determined that an environmental impact statement should be prepared, it and other related documentation will be prepared by the directorate responsible for the action in accordance with section 102(2)(c) of the Act, this part, and the CEQ regulations. The responsible directorate will be in close communication with the grant or contract applicant and may have to rely extensively on his or her input in preparing the EIS. However, once a document is prepared it shall be submitted to the Chairman who, after such review by the Committee as is deemed necessary by the Chairman, shall transmit the document as required by CEQ regulations and this part. If the Chairman considers a document unsatisfactory, he or she shall return it to the responsible directorate for revision prior to an award decision.
Specifically, the following steps, as discussed in the CEQ regulations, will be followed in preparing an EIS:
- (1) A notice of intent to prepare a draft EIS will be published as described in 40 CFR 1501.7.
- (2) Scoping, as described in 40 CFR 1501.7, will be conducted.
- (3) The format and contents of the draft and final EIS shall be as discussed in 40 CFR part 1502.
- (4) Comments on the draft EIS shall be invited as set forth in 40 CFR 1503.1. The minimum period to be afforded for comments on a draft EIS shall be 45 days, unless a lesser period is necessary to comply with other specific statutory requirements or in case of emergency circumstances, as described in 40 CFR 1506.11.
- (5) The requirements of 40 CFR 1506.9 for filing of documents with the Environmental Protection Agency shall be followed.
- (6) The responsible directorate shall examine carefully the basis on which supportive studies have been conducted to assure that such studies are objective and comprehensive in scope and in depth.
- (7) The Act requires that the decisionmaking involved “utilize a systematic, interdisciplinary approach that will insure the integrated use of the natural and social sciences and the environmental design arts.” If such disciplines are not present on the NSF staff, appropriate use should be made of personnel of Federal, State, and local agencies, universities, non-profit organizations, or private industry.
- (8) A copy of the draft EIS or the final EIS (or a summary, if the size of the EIS does not make this practical) shall be included in and accompany the appropriate proposal throughout the NSF internal review and approval process.