(a) A CAA must be modified when there is:
- (1) A modification to the allocation agreement;
- (2) Inclusion of additional leases, unit PAs, or CAs are proposed in the CAA; or
- (3) Termination of or permanent production cessation from any of the leases, unit PAs, or CAs within the CAA.
(b) To request a modification of a CAA, all operators must submit to the AO:
- (1) A completed Sundry Notice describing the modification requested;
- (2) A new allocation methodology, including an allocation methodology which includes allocation of produced water and an example of how the methodology is applied, if appropriate; and
- (3) Certification by each operator in the CAA that it agrees to the CAA modification.
- (c) A change in operator does not trigger the need to modify a CAA.