(3) The Responsible Official must conduct the scoping process consistent with 40 CFR 1501.7 and any applicable EPA public participation regulations (e.g., 40 CFR Part 25).
- (i) Publication of the NOI in the Federal Register begins the scoping process.
- (ii) The Responsible Official must ensure that the scoping process for an EIS allows a minimum of thirty (30) days for the receipt of public comments.
- (iii) The Responsible Official may hold one or more public meetings as part of the scoping process for an EPA EIS. The Responsible Official must announce the location, date, and time of public scoping meetings in the NOI or by other appropriate means, such as additional notices in the Federal Register, news releases to the local media, or letters to affected parties. Public scoping meetings should be held at least fifteen (15) days after public notification.
- (iv) The Responsible Official must use appropriate means to publicize the availability of draft and final EISs and the time and place for public meetings or hearings on draft EISs. The methods chosen for public participation must focus on reaching persons who may be interested in the proposed action. Such persons include those in potentially affected communities where the proposed action is known or expected to have environmental impacts including minority communities, low-income communities, or federally-recognized Indian tribal communities.
- (v) The Responsible Official must circulate the draft and final EISs consistent with 40 CFR 1502.19 and any applicable EPA public participation regulations and in accordance with the 45-day public review period for draft EISs and the 30-day public review period for final EISs (see § 6.209 of this part). Consistent with section 6.209(b) of this part, the Responsible Official may establish a longer public comment period for a draft or final EIS.
- (vi) After preparing a draft EIS and before preparing a final EIS, the Responsible Official must solicit the comments of appropriate federal agencies, state and/or local governments, and/or federally-recognized Indian tribes, and the public (see 40 CFR 1503.1). The Responsible Official must respond in the final EIS to substantive comments received (see 40 CFR 1503.4).
- (vii) The Responsible Official may conduct one or more public meetings or hearings on the draft EIS as part of the public involvement process. If meetings or hearings are held, the Responsible Official must make the draft EIS available to the public at least thirty (30) days in advance of any meeting or hearing.