The Secretary makes funds available to a grantee during a project period using the following procedure:
- (a) Upon final approval of the grant proposal, the Secretary authorizes a project period of up to 60 months based upon the nature of the grant proposal and the time needed to complete the project.
- (b) The Secretary then initially makes available to the grantee 10 percent of the total award amount.
- (c) After the grantee submits a copy of the emergency or modernization contract approved by the grantee's governing board, the Secretary makes available 80 percent of the total award amount to a grantee.
(d) The Secretary makes available up to the remaining 10 percent of the total award amount to the grantee after the grantee submits a statement that—
- (1) Details any earnings, savings, or interest;
(2) Certifies that—
- (i) The project is fully completed; and
- (ii) All the awarded funds have been spent for grant purposes; and
(3) Is signed by the—
- (i) Chairperson of the governing board;
- (ii) Superintendent of schools; and
(iii) Architect of the project.
(Authority: 20 U.S.C. 7707(b))