- (a) For each grant, you must annually report to us the performance and financial information that we request.
- (b) Upon completion of each grant, you must report to us final performance and financial information that we request.
(c) You must use the AML inventory to maintain a current list of AML problems and to report annual reclamation accomplishments with grant funds.
- (1) If you conduct coal reclamation projects or noncoal reclamation projects under part 875 of this chapter, you must update the AML inventory for each reclamation project as you fund it.
- (2) You must update the AML inventory for each reclamation project you complete as you complete it.
- (3) We must approve any amendments to the AML inventory after December 20, 2006. We define amendment as any coal problems added to the AML inventory in a new or existing problem area.
[73 FR 67642, Nov. 14, 2008, as amended at 80 FR 6447, Feb. 5, 2015]