Your SEMS program must require that the commissioning process include a pre-startup safety and environmental review for new and significantly modified facilities that are subject to this subpart to confirm that the following criteria are met:
- (a) Construction and equipment are in accordance with applicable specifications.
- (b) Safety, environmental, operating, maintenance, and emergency procedures are in place and are adequate.
- (c) Safety and environmental information is current.
- (d) Hazards analysis recommendations have been implemented as appropriate.
- (e) Training of operating personnel has been completed.
- (f) Programs to address management of change and other elements of this subpart are in place.
- (g) Safe work practices are in place.