30 C.F.R. § 250.917
(b) Primary duties of the CVA during the fabrication phase include the following:
| Type of facility . . . | The CVA must . . . |
|---|---|
| (1) For all fixed platforms and non-ship-shaped floating facilities, | Make periodic onsite inspections while fabrication is in progress and must verify the following fabrication items, as appropriate: |
| (i) Quality control by lessee and builder; | |
| (ii) Fabrication site facilities; | |
| (iii) Material quality and identification methods; | |
| (iv) Fabrication procedures specified in the approved plan, and adherence to such procedures; | |
| (v) Welder and welding procedure qualification and identification; | |
| (vi) Structural tolerances specified and adherence to those tolerances; | |
| (vii) The nondestructive examination requirements, and evaluation results of the specified examinations; | |
| (viii) Destructive testing requirements and results; | |
| (ix) Repair procedures; | |
| (x) Installation of corrosion-protection systems and splash-zone protection; | |
| (xi) Erection procedures to ensure that overstressing of structural members does not occur; | |
| (xii) Alignment procedures; | |
| (xiii) Dimensional check of the overall structure, including any turrets, turret-and-hull interfaces, any mooring line and chain and riser tensioning line segments; and | |
| (xiv) Status of quality-control records at various stages of fabrication. | |
| (2) For all floating facilities, | Ensure that the requirements of the U.S. Coast Guard floating for structural integrity and stability, e.g., verification of center of gravity, etc., have been met. The CVA must also consider: |
| (i) Drilling, production, and pipeline risers, and riser tensioning systems (at least for the initial fabrication of these elements); | |
| (ii) Turrets and turret-and-hull interfaces; | |
| (iii) Foundation pilings and templates, and anchoring systems; and | |
| (iv) Mooring or tethering systems. |
(c) The CVA must submit interim reports and a final report to the Regional Supervisor, and to you, during the fabrication phase in accordance with the approved schedule required by § 250.911(d). In each interim and final report the CVA must: