(a) You must use the DWOP process for any project that meets any of the following criteria:
- (1) Is planned in water depths greater than 1000 ft;
- (2) Will use subsea tieback development technology, regardless of water depth; or
- (3) Will use any new or unusual technology for any drilling, completion, workover, intervention, injection, production, pipeline, platform, decommissioning, or abandonment project.
- (b) If you are unsure if your project will use subsea tieback development technology or new or unusual technology, contact the Regional Supervisor for guidance.