(a) FmHA certifications upon completion. Upon completion of the project, FmHA shall inspect the project and, if determined to be acceptable, submit to the HUD field office the following certifications:
- (1) The project has been completed in accordance with the requirements of the Agreement;
- (2) The project is in good and tenantable condition;
- (3) There are no defects or deficiencies in the project other than punchlist items, or incomplete work awaiting seasonal opportunity;
- (4) There has been no change in management capability.