(b) Construction activities. Recipients of funds for rehabilitation or new construction must meet the following standards:
- (1) Construction activities must begin within 9 months of the later of signing of the grant agreement or of signing an addendum to the grant agreement authorizing use of grant funds for the project.
- (2) Construction activities must be completed within 24 months of signing the grant agreement.
- (3) Activities that cannot begin until after construction activities are completed must begin within 3 months of the date that construction activities are completed.