(d) When a State DOT awards the contract for completion of a Federal-aid contract previously terminated for default, the construction amount eligible for Federal participation on the project should not exceed whichever amount is the lesser, either:
- (1) The amount representing the payments made under the original contract plus payments made under the new contract; or
- (2) The amount representing what the cost would have been if the construction had been completed as contemplated by the plans and specifications under the original contract.