(a) Not later than 90 days after completing an investigation, a Team shall issue a public report which includes:
- (1) An analysis of the likely technical cause or causes of the building failure investigated;
- (2) Any technical recommendations for changes to or the establishment of evacuation or emergency response procedures;
- (3) Any recommended specific improvements to building standards, codes, and practices; and
- (4) Recommendations for research and other appropriate actions needed to help prevent future building failures.