(a) No person or DOE personnel shall take or cause to be taken any action inconsistent with the requirements of:
- (1) This part; or
- (2) Any program, plan, schedule, or other process established by this part.
- (b) With respect to a particular DOE activity, contractor management shall be responsible for compliance with the requirements of this part.
- (c) Where there is no contractor for a DOE activity, DOE shall ensure implementation of and compliance with the requirements of this part.
- (d) Nothing in this part shall be construed as limiting actions that may be necessary to protect health and safety.
- (e) For those activities that are required by §§ 835.102, 835.901(e), 835.1202 (a), and 835.1202(b), the time interval to conduct these activities may be extended by a period not to exceed 30 days to accommodate scheduling needs.
[58 FR 65485, Dec. 14, 1993, as amended at 63 FR 59682, Nov. 4, 1998]