10 C.F.R. § 53.1640
(a) Reportable events.
(2) The licensee must report—
(i)
(B) Any operation or condition which was prohibited by the plant's Technical Specifications except when—
(1) The Technical Specification is administrative in nature;
(2) The event consisted solely of a case of a late surveillance test where the oversight was corrected, the test was performed, and the equipment was found to be capable of performing its specified safety functions; or
(3) The Technical Specification was revised prior to discovery of the event such that the operation or condition was no longer prohibited at the time of the event.
(ii) Any event or condition that resulted in—
(iv) Any event or condition that resulted in inadvertent operation of any structures, systems, and component classified as safety-related (SR) for an identified safety function under § 53.460 or the unplanned sole reliance on an SR system for those systems that are in constant operation, except when—
(B) The actuation was invalid and—
(1) Occurred while the system was properly removed from service; or
(2) Occurred after the safety function had been already completed.
(vii)
(B) Events covered in paragraph (a)(2)(vii)(A) of this section may include cases of procedural error, equipment failure, and/or discovery of a design, analysis, fabrication, construction, and/or procedural inadequacy. However, licensees are not required to report an event pursuant to paragraph (a)(2)(vii)(A) of this section if the event results from—
(1) A shared dependency among trains or channels that is a natural or expected consequence of the approved plant design; or
(2) Normal and expected wear or degradation.
(viii)
(b) Contents. The LER must contain—
(2)
(ii) The narrative description must include the following specific information as appropriate for the particular event:
(3) An assessment of the safety consequences and implications of the event. This assessment must include—