(3) Inspections, tests, analyses, and acceptance criteria. The proposed inspections, tests, and analyses, including those applicable to emergency planning, that the licensee must perform, and the acceptance criteria that are necessary and sufficient to provide reasonable assurance that, if the inspections, tests, and analyses are performed and the acceptance criteria met, the facility has been constructed and will be operated in conformity with the COL, the provisions of the Act, and the Commission's rules and regulations.
- (i) If the application references an early site permit with ITAAC, the early site permit ITAAC must apply to those aspects of the COL which are approved in the early site permit.
- (ii) If the application references a standard design certification, the ITAAC contained in the certified design must apply to those portions of the facility design which are approved in the standard design certification.
- (iii) If the application references an ML, the ITAAC contained in the ML must apply to those portions of the facility design which are approved in the ML.
- (iv) If the application references an early site permit with ITAAC, a standard design certification, an ML, or a combination thereof, the application may include a notification that a required inspection, test, or analysis in the ITAAC has been successfully completed and that the corresponding acceptance criterion has been met. The Federal Register notice required by § 53.1422 of this chapter must indicate that the application includes this notification.