Cal. Pub. Util. Code § 2827
(b) As used in this section, the following terms have the following meanings:
(4)
(B)
(C)
(c)
(3)
(4)
(B) The commission shall require every large electrical corporation to make the standard contract or tariff available to eligible customer-generators, continuously and without interruption, until such times as the large electrical corporation reaches its net energy metering program limit or July 1, 2017, whichever is earlier. A large electrical corporation reaches its program limit when the combined total peak demand of all electricity used by eligible customer-generators served by all the electric utilities in the large electrical corporation’s service area furnishing net energy metering to eligible customer-generators exceeds 5 percent of the aggregate customer peak demand of those electric utilities. For purposes of calculating a large electrical corporation’s program limit, “aggregate customer peak demand” means the highest sum of the noncoincident peak demands of all of the large electrical corporation’s customers that occurs in any calendar year. To determine the aggregate customer peak demand, every large electrical corporation shall use a uniform method approved by the commission. The program limit calculated pursuant to this paragraph shall not be less than the following:
(e)
(f)
(h) For eligible customer-generators, the net energy metering calculation shall be made by measuring the difference between the electricity supplied to the eligible customer-generator and the electricity generated by the eligible customer-generator and fed back to the electrical grid over a 12-month period. The following rules shall apply to the annualized net metering calculation:
(2) At the end of each 12-month period, where the electricity supplied during the period by the electric utility exceeds the electricity generated by the eligible residential or small commercial customer-generator during that same period, the eligible residential or small commercial customer-generator is a net electricity consumer and the electric utility shall be owed compensation for the eligible customer-generator’s net kilowatthour consumption over that 12-month period. The compensation owed for the eligible residential or small commercial customer-generator’s consumption shall be calculated as follows:
(4)
(5)
(A) The ratemaking authority shall establish a net surplus electricity compensation valuation to compensate the net surplus customer-generator for the value of net surplus electricity generated by the net surplus customer-generator. The commission shall establish the valuation in a ratemaking proceeding. The ratemaking authority for a local publicly owned electric utility shall establish the valuation in a public proceeding. The net surplus electricity compensation valuation shall be established so as to provide the net surplus customer-generator just and reasonable compensation for the value of net surplus electricity, while leaving other ratepayers unaffected. The ratemaking authority shall determine whether the compensation will include, where appropriate justification exists, either or both of the following components:
(6)
(i) Notwithstanding any other provisions of this section, paragraphs (1), (2), and (3) shall apply to an eligible customer-generator with a capacity of more than 10 kilowatts, but not exceeding one megawatt, that receives electric service from a local publicly owned electric utility that has elected to utilize a co-energy metering program unless the local publicly owned electric utility chooses to provide service for eligible customer-generators with a capacity of more than 10 kilowatts in accordance with subdivisions (g) and (h):