(a) This article applies in any of the following circumstances:
(4)
(A) An electrical corporation may file an application requesting the commission to issue a financing order to authorize the recovery of verified incremental undercollection amounts for calendar year 2020 through fixed recovery charges pursuant to this article, if an electrical corporation’s annual true-up advice letter is accepted and either or both of the following incremental undercollection amounts are verified for calendar year 2020:
(b) For purposes of this article, the following terms shall have the following meanings:
(4) “Financing costs” means the costs to issue, service, repay, or refinance recovery bonds, whether incurred or paid upon issuance of the recovery bonds or over the life of the recovery bonds, if they are approved for recovery by the commission in a financing order. “Financing costs” may include any of the following:
(7) “Fixed recovery charges” means those nonbypassable rates and other charges, including, but not limited to, distribution, connection, disconnection, and termination rates and charges, that are authorized by the commission in a financing order to recover both of the following:
(10) “Recovery costs” means any of the following:
(11)
(A) “Recovery property” means the property right created pursuant to this article, including, without limitation, the right, title, and interest of the electrical corporation or its transferee:
(12)