Cal. Pub. Util. Code § 769.5
(b) The expedited distribution grid interconnection dispute resolution process shall include the following elements:
(1) A distribution grid interconnection technical panel consisting of at least eight individuals selected by the commission. Four of the technical panel members shall be from electrical corporations and four shall not be from electrical corporations. The commission shall determine the length of the term of each member. A member shall not participate as a review panel member for the dispute resolution process for a contested interconnection application in any of the following situations: