Effective Jan 1, 2019Added by Stats. 2018, Ch. 561, Sec. 2. (SB 1090) Effective January 1, 2019.
(a) The commission shall approve both of the following:
(1) The full funding for the community impact mitigation settlement proposed in Application 16-08-006.
(2) The full funding for the employee retention program proposed in Application 16-08-006.
(b) The commission shall ensure that integrated resource plans are designed to avoid any increase in emissions of greenhouse gases as a result of the retirement of the Diablo Canyon Units 1 and 2 powerplant.
(c) The commission shall establish an expedited advice letter process for the approval and implementation pursuant to subdivision (a) of the community impact mitigation settlement and the employee retention program.