Cal. Health & Safety Code § 130060
(a)
(1) After January 1, 2008, a general acute care hospital building that is determined to be a potential risk of collapse or pose significant loss of life shall only be used for nonacute care hospital purposes, unless an extension of this deadline has been granted and either of the following occurs before the end of the extension:
(3) Prior to granting an extension of the January 1, 2008, deadline pursuant to this section, the department shall do all of the following:
(b)
(3) To receive the five-year extension, a single building containing all of the basic services or at least one building within the contiguous grouping of hospital buildings shall have obtained a building permit prior to 1973 and this building shall be evaluated and classified as a nonconforming, Structural Performance Category-1 (SPC-1) building. The classification shall be submitted to and accepted by the Department of Health Care Access and Information. The identified hospital building shall be exempt from the requirement in subdivision (a) until January 1, 2013, if the hospital agrees that the basic service or services that were provided in that building shall be provided, on or before January 1, 2013, as follows:
(f)
(2) The department may grant the additional extension if the hospital building subject to the extension meets all of the following criteria:
(D) The hospital submitted a construction timeline at least two years prior to the applicable deadline for the building demonstrating the hospital’s intent to meet the applicable deadline. The timeline shall include all of the following:
(3) The department may grant the additional extension if the hospital building subject to the extension meets all of the following criteria:
(D) The hospital submitted, by December 31, 2011, a construction timeline for the building demonstrating the hospital’s intent and ability to meet the deadline of December 31, 2014. The timeline shall include all of the following:
(5) The department may grant the additional extension if the hospital building subject to the extension meets all of the following criteria:
(D) The hospital submits, prior to January 1, 2012, a construction timeline for the building demonstrating the hospital’s intent and ability to meet the applicable deadline. The timeline shall include all of the following:
(g)
(2) The hospital building subject to the extension shall meet all of the following milestones, unless the hospital building is reclassified as SPC-2 or higher as a result of its Hazards US score:
(i)
(2) The hospital owner seeking the extension shall submit a written request that includes a timeline specifying how the hospital intends to meet the new deadline, including the construction document submission dates. The following timeline shall be met for construction document submissions: