(a)
(1) Notwithstanding any local law, if a local government’s planning director or equivalent position determines that an adaptive reuse project submitted pursuant to this article is consistent with the objective planning standards specified in Section 65658.5 and Section 65658.6, if applicable, the local government shall approve the adaptive reuse project within the following timeframes:
(2) Upon a determination that an adaptive reuse project submitted pursuant to this section is in conflict with any of the objective planning standards specified in Section 65658.5 or Section 65658.6, if applicable, the local government staff or relevant local planning and permitting department that made the determination shall provide the development proponent written documentation of which standard or standards the development conflicts with, and an explanation for the reason or reasons the development conflicts with that standard or standards within the following timeframes:
(b)
(1)
(c)
(1) Notwithstanding any law, a local government, whether or not it has adopted an ordinance governing automobile parking requirements in multifamily developments, shall not impose automobile parking standards for an adjacent portion of the project that was approved pursuant to this article in any of the following instances:
(d) Notwithstanding any other law, a local government shall not require any of the following prior to approving an adaptive reuse project that meets the requirements of this article:
(2)
(e)
(1) If a local government approves an adaptive reuse project pursuant to this article, then, notwithstanding any other law, that approval shall not expire if the project satisfies both of the following requirements:
(2)
(A) If a local government approves an adaptive reuse project pursuant to this article, and the project does not satisfy the requirements of subparagraphs (A) and (B) of paragraph (1), that approval shall remain valid for three years from the date of the final action establishing that approval, or if litigation is filed challenging that approval, from the date of the final judgment upholding that approval. Approval shall remain valid for a project provided construction activity, including demolition and grading activity, on the development site has begun pursuant to a permit issued by the local jurisdiction and is in progress. For purposes of this subdivision, “in progress” means one of the following:
(f)
(1)
(3) Notwithstanding paragraph (1), the local government may apply objective planning standards to an adjacent portion of the project adopted after the project application was first submitted to the requested modification in any of the following instances: