Cal. Code Regs. tit. 8, § 1710
(a) Scope and application.
(1) This section sets forth requirements to protect employees from the hazards associated with steel erection activities involved in the construction, alteration, and/or repair of single and multi-story buildings, bridges, and other structures where steel erection occurs. The requirements of this section apply to employers engaged in steel erection unless otherwise specified.
Exception: This section does not cover electrical transmission towers, communication and broadcast towers, or tanks.
Note: Additional requirements for work on steel framed structures are contained in Article 20, Section 1635(b) of these orders.
(b) Definitions.
“Anchored bridging” means that the steel joist bridging is connected to a bridging terminus point.
“Bolted diagonal bridging” means diagonal bridging that is bolted to a steel joist or joists.
“Bridging clip” means a device that is attached to the steel joist to allow the bolting of the bridging to the steel joist.
“Bridging terminus point” means a wall, a beam, tandem joists (with all bridging installed and a horizontal truss in the plane of the top chord) or other element at an end or intermediate point(s) of a line of bridging that provides an anchor point for the steel joist bridging.
“Cold forming” means the process of using press brakes, rolls, or other methods to shape steel into desired cross sections at room temperature.
“Column” means a load-carrying vertical member that is part of the primary skeletal framing system. Columns do not include posts.
“Connector” means an employee who, working with hoisting equipment, is placing and connecting beams or other structural members.
“Constructibility” means the ability to erect structural steel members in accordance with Section 1710 without having to alter the over-all structural design.
“Construction load” (for joist erection) means any load other than the weight of the employee(s), the joists and the bridging bundle.
“Controlled Decking Zone (CDZ)” means an area established specifically for the initial placement and securing of metal decking where access to the area is restricted and work may take place without the use of a personal fall protection system when the provisions of Section 1710(n) are met.
“Controlled load lowering” means lowering a load by means of a mechanical hoist drum device that allows a hoisted load to be lowered with maximum control using the gear train or hydraulic components of the hoist mechanism. Controlled load lowering requires the use of the hoist drive motor, rather than the load hoist brake, to lower the load.
“Controlling contractor” means a prime contractor, general contractor, construction manager or any other legal entity which has the overall responsibility for the construction of the project -- its planning, quality and completion.
“Critical lift” (used in Appendix C to Section 1710) means a lift that exceeds 75 percent of the rated capacity of the crane or derrick, or requires the use of more than one crane or derrick.
“Derrick floor” (working floor) means an elevated floor of a building or structure that has been designated to receive hoisted pieces of steel prior to final placement.
“Double connection” means an attachment method where the connection point is intended for two pieces of steel which share common bolts on either side of a central piece.
“Double connection seat” means a structural attachment that, during the installation of a double connection, supports the first member while the second member is connected.
“Erection bridging” means the bolted diagonal bridging that is required to be installed prior to releasing the hoisting cables from the steel joists.
“Girt” (in systems-engineered metal buildings) means a “Z” or “C” shaped member formed from sheet steel spanning between primary framing and supporting wall material.
“Metal decking” means a commercially manufactured, structural grade, cold rolled metal panel formed into a series of parallel ribs; for this section, this includes metal floor and roof decks, standing seam metal roofs, other metal roof systems and other products such as bar gratings, checker plate, expanded metal panels, and similar products. After installation and proper fastening, these decking materials serve a combination of functions including, but not limited to: a structural element designed in combination with the structure to resist, distribute and transfer loads, stiffen the structure and provide a diaphragm action; a walking/working surface; a form for concrete slabs; a support for roofing systems; and a finished floor or roof.
“Multiple lift rigging” means rigging manufactured by rigging suppliers that facilitates the attachment of up to five independent loads to the hoist rigging of a crane.
“Permanent floor” means a structurally completed floor at any level or elevation (including slab on grade).
“Post” means a structural member with a longitudinal axis that is essentially vertical, that weighs 300 pounds or less and is axially loaded (a load presses down on the top end), or is not axially loaded, but is laterally restrained by the above member. Posts typically support stair landings, wall framing, mezzanines and other substructures.
“Project structural engineer of record” means the registered, California licensed engineer responsible for the design of structural steel framing and whose seal appears on the structural contract documents.
“Purlin” (in systems-engineered metal buildings) means a “Z” or “C” shaped member formed from sheet steel spanning between primary framing and supporting roof material.
“Safety deck attachment” means an initial attachment that is used to secure an initially placed sheet of decking to keep proper alignment and bearing with structural support members.
“Shear connector” means headed steel studs, steel bars, steel lugs, and similar devices which are attached to a structural member for the purpose of achieving composite action with concrete.
“Steel erection” means the construction, alteration or repair of steel buildings, bridges and other structures, including the installation of metal decking and all planking used during the process of erection.
“Steel joist” means an open web, secondary load-carrying member of 144 feet (43.9 m) or less, designed by the manufacturer, used for the support of floors and roofs. This does not include structural steel trusses or cold-formed joists.
“Steel joist girder” means an open web, primary load-carrying member, designed by the manufacturer, used for the support of floors and roofs. This does not include structural steel trusses.
“Steel truss” means an open web member designed of structural steel components by the project structural engineer of record. For the purposes of this section, a steel truss is considered equivalent to a solid web structural member.
“Structural steel” means a steel member, or a member made of a substitute material. These members include, but are not limited to, steel joists, joist girders, purlins, columns, beams, trusses, splices, seats, metal decking, girts, and all bridging, and cold formed metal framing which is integrated with the structural steel framing of a building.
“Systems-engineered metal building” means a metal, field-assembled building system consisting of framing, roof and wall coverings. Typically, many of these components are cold-formed shapes. These individual parts are fabricated in one or more manufacturing facilities and shipped to the job site for assembly into the final structure. The engineering design of the system is normally the responsibility of the systems-engineered metal building manufacturer.
“Tank” means a container for holding gases, liquids or solids.
(c) Site layout and construction sequence.
(1) Approval to begin steel erection. Before authorizing the commencement of steel erection, the controlling contractor shall ensure that the steel erector is provided with the following written notifications:
(3) Site layout. The controlling contractor shall ensure that the following is provided and maintained:
(A) Adequate access roads into and through the site for the safe delivery and movement of derricks, cranes, trucks, other necessary equipment, and the material to be erected and means and methods for pedestrian and vehicular control.
Exception: This requirement does not apply to roads outside of the construction site.
(d) Hoisting and rigging.
(1) Working under loads.
(A) Routes for suspended loads shall be pre-planned to ensure that no employee is working below a suspended load except as necessary for:
(B) When working under suspended loads, the following criteria shall be met:
(2) Multiple Lift Rigging Procedure.
(A) A multiple lift shall only be performed if the following criteria are met:
(C) The total load shall not exceed:
(D) The multiple lift rigging assembly shall be rigged with members:
(9) Safety latches on hooks shall not be deactivated or made inoperable except:
(B) When the steel erector develops and implements a site-specific erection plan that ensures the load will not travel over or expose employees in other trades to the hazards of suspended loads.
Note: Other applicable regulations pertaining to hoisting and rigging operations for the use of cranes and derricks in steel erection construction are contained in the General Industry Safety Orders, Group 13, Cranes and Other Hoisting Equipment.
(e) Walking/working surfaces.
(1) Shear connectors and other similar devices.
(B) Installation of shear connectors on composite floors, roofs and bridge decks. When shear connectors are used in construction of composite floors, roofs and bridge decks, employees shall lay out and install the shear connectors after the metal decking has been installed, using the metal decking as a working platform.
Note: Section 1710(n)(8) prohibits the installation of shear connectors within a controlled decking zone.
(f) Column anchorage.
(1) General requirements for erection stability.
(A) All columns shall be anchored by a minimum of 4 anchor rods (anchor bolts).
Exception: When columns are braced or guyed to provide the stability to support an eccentric load as specified in subsection (f)(1)(B) of this section.
(2) Repair, replacement or field modification of anchor rods (anchor bolts).
(A) Anchor rods (anchor bolts) shall not be repaired, replaced or field-modified without the approval of the project structural engineer of record.
Note: Minor adjustment of anchor rods (anchor bolts) that do not affect the structural integrity of anchor rods (anchor bolts) are not considered “repairs” for the purposes of this subsection.
(g) Beams and columns.
(4) Double connections at columns and/or at beam webs over a column.
(6) Perimeter columns. Perimeter columns shall not be erected unless:
(h) Open web steel joists.
(1) General.
(A) Except as provided in subsection (h)(1)(B) of this section, where steel joists are used and columns are not framed in at least two directions with solid web structural steel members, a steel joist shall be field-bolted at the column to provide lateral stability to the column during erection. For the installation of this joist:
(B) Where constructibility does not allow a steel joist to be installed at the column:
1. An alternate means of stabilizing joists shall be installed on both sides near the column and shall:
(G) Field-bolted joists.
(2) Attachment of steel joists and steel joist girders.
(3) Erection of steel joists.
(E) When permanent bridging terminus points cannot be used during erection, additional temporary bridging terminus points are required to provide stability. (See Appendix A of this section.)
Table A. Erection Bridging for Short Span Joists
Joist
Span -- Feet
8K1
NM
10K1
NM
12K1
23-0
12K3
NM
12K5
NM
14K1
27-0
14K3
NM
14K4
NM
14K6
NM
16K2
29-0
16K3
30-0
16K4
32-0
16K5
32-0
16K6
NM
16K7
NM
16K9
NM
18K3
31-0
18K4
32-0
18K5
33-0
18K6
35-0
18K7
NM
18K9
NM
18K10
NM
20K3
32-0
20K4
34-0
20K5
34-0
20K6
36-0
20K7
39-0
20K9
39-0
20K10
NM
22K4
34-0
22K5
35-0
22K6
36-0
22K7
40-0
22K9
40-0
22K10
NM
22K11
NM
24K4
36-0
24K5
38-0
24K6
39-0
24K7
43-0
24K8
43-0
24K9
44-0
24K10
NM
24K12
NM
26K5
38-0
26K6
39-0
26K7
43-0
26K8
44-0
26K9
44-0
26K10
49-0
26K12
NM
28K6
40-0
28K7
43-0
28K8
44-0
28K9
45-0
28K10
49-0
28K12
53-0
30K7
44-0
30K8
45-0
30K9
45-0
30K10
50-0
30K11
52-0
30K12
54-0
10KCS1
NM
10KCS2
NM
10KCS3
NM
12KCS1
NM
12KCS2
NM
12KCS3
NM
14KCS1
NM
14KCS2
NM
14KCS3
NM
16KCS2
NM
16KCS3
NM
16KCS4
NM
16KCS5
NM
18KCS2
35-0
18KCS3
NM
18KCS4
NM
18KCS5
NM
20KCS2
36-0
20KCS3
39-0
20KCS4
NM
20KCS5
NM
22KCS2
36-0
22KCS3
40-0
22KCS4
NM
22KCS5
NM
24KCS2
39-0
24KCS3
44-0
24KCS4
NM
24KCS5
NM
26KCS2
39-0
26KCS3
44-0
26KCS4
NM
26KCS5
NM
28KCS2
40-0
28KCS3
45-0
28KCS4
53-0
28KCS5
53-0
30KCS3
45-0
30KCS4
54-0
30KCS5
54-0
NM=diagonal bolted bridging not mandatory.
Table B. Erection Bridging for Long Span Joists
Joist
Span -- Feet
18LH02
33-0.
18LH03
NM.
18LH04
NM.
18LH05
NM.
18LH06
NM.
18LH07
NM.
18LH08
NM.
18LH09
NM.
20LH02
33-0.
20LH03
38-0.
20LH04
NM.
20LH05
NM.
20LH06
NM.
20LH07
NM.
20LH08
NM.
20LH09
NM.
20LH10
NM.
24LH03
35-0.
24LH04
39-0.
24LH05
40-0.
24LH06
45-0.
24LH07
NM.
24LH08
NM.
24LH09
NM.
24LH10
NM.
24LH11
NM.
28LH05
42-0.
28LH06
46-0.
28LH07
54-0
28LH08
54-0
28LH09
NM.
28LH10
NM.
28LH11
NM.
28LH12
NM.
28LH13
NM.
32LH06
47-0 through 60-0.
32LH07
47-0 through 60-0.
32LH08
55-0 through 60-0.
32LH09
NM through 60-0.
32LH10
NM through 60-0.
32LH11
NM through 60-0.
32LH12
NM through 60-0.
32LH13
NM through 60-0.
32LH14
NM through 60-0.
32LH15
NM through 60-0.
36LH07
47-0 through 60-0.
36LH08
47-0 through 60-0.
36LH09
57-0 through 60-0.
36LH10
NM through 60-0.
36LH11
NM through 60-0.
36LH12
NM through 60-0.
36LH13
NM through 60-0.
36LH14
NM through 60-0.
36LH15
NM through 60-0.
NM=diagonal bolted bridging not mandatory.
(4) Erection bridging.
(A) Where the span of the steel joist is equal to or greater than the span shown in Tables A and B, the following shall apply:
(B) Where the span of the steel joist is over 60 feet (18.3 m) through 100 feet (30.5 m), the following shall apply:
(C) Where the span of the steel joist is over 100 feet (30.5 m) through 144 feet (43.9 m), the following shall apply:
(F) When bolted diagonal erection bridging is required by this section, the following shall apply:
(5) Landing and placing loads.
(D) No bundle of decking may be placed on steel joists until all bridging has been installed and anchored and all joist bearing ends attached, unless all of the following conditions are met:
(i) Systems-engineered metal buildings.
(6) Both ends of all steel joists or cold-formed joists shall be fully bolted and/or welded to the support structure before:
(j) Falling object protection.
(k) Permanent Flooring--Skeleton Steel Construction in Tiered Buildings.
(l) Temporary Flooring--Skeleton Steel Construction in Multistory Buildings.
(3) The exposed edges of all temporary planked and metal decked floors at the periphery of the building, or at interior openings, such as stairways and elevator shafts shall be protected by a single ⅜ -inch minimum diameter wire rope of 13,500 pounds minimum breaking strength located between 42 and 45 inches above design finish floor height. Other guardrail protection may be used if equal fall protection is provided.
Note: If the periphery fall protection is intended to be used as a catenary line, it shall meet the provisions of Section 1710(m)(4).
(4) Midrail protection.
(5) Installation of Metal Decking.
(7) Where skeleton steel is being erected, a tightly planked and substantial floor shall be maintained within two stories or 30 feet, whichever is less, below and directly under that portion of each tier of beams on which any work is being performed.
Note: Where a planked floor is not practical, subsection (l)(2) of this section applies.
(m) Working and Traveling on the Skeleton Steel of Multistory Buildings or Structures.
(1) Connecting.
(B) At heights over 15 and up to 30 feet above a lower level, connectors shall be provided with a personal fall arrest system, positioning device system or fall restraint system and wear the equipment necessary to be able to be tied off; or be provided with other means of protection from fall hazards in accordance with subsection (m).
Note: For fall protection requirements associated with work above reinforcing steel and similar projections, see Section 1712 of the Construction Safety Orders.
(C) Shinning of Columns.
(2) Work Other Than Connecting.
When performing any other work at a work point, iron workers shall be provided with and use personal fall protection as described in Article 24 where the fall distance is greater than 15 feet.
(3) Traveling at Periphery or Interior of Building.
(A) When moving from work point to work point or releasing slings, and the fall distance is greater than 30 feet or two stories, whichever is less, connectors:
(B) When moving from work point to work point or releasing slings, and the fall distance is greater than 15 feet for other than connecting, iron workers:
(n) Controlled Decking Zone (CDZ). A CDZ is an area established specifically for the initial placement and securing of metal decking where access to the area is restricted and work may take place without the use of a personal fall protection system.
(4) The employer shall document the reasons why the use of conventional fall protection systems (guardrails, personal fall arrest systems, positioning device systems, fall restraint systems or safety nets) are infeasible or why their use would create a greater hazard.
(5) Where a CDZ is being used, the employer shall assure that a safety monitoring system is provided and shall designate a competent person to monitor the safety of employees within the CDZ. The safety monitor shall comply with the following requirements:
(6) In each CDZ, the following shall apply:
(C) The boundaries of a CDZ shall be designated and clearly marked. The CDZ shall be defined by a control line or by any equivalent means that restrict access.
(o) Custody of guardrail systems. Wire rope or other guardrail protection provided by the steel erector shall remain in the area where steel erection activity has been completed, to be used by other trades, only if the controlling contractor or its authorized representative:
(q) Training.
(2) Fall hazard training. The employer shall provide a training program for all employees exposed to fall hazards. The program shall include training and instruction in the following areas:
(3) Special training programs. In addition to the training required in subsections (q)(1) and (q)(2) of this section, the employer shall provide special training to employees engaged in the following activities.
(A) Multiple lift rigging procedure. The employer shall ensure that each employee who performs multiple lift rigging has been provided training in the hazards associated with multiple lifts including the following areas:
(B) Connector procedures. The employer shall ensure that each connector has been provided training in the following areas:
(C) Controlled Decking Zone Procedures. Where CDZs are being used, the employer shall assure that each employee has been provided training in the following areas:
The following provisions supplement the requirements of Section 1509 “Injury and Illness Prevention Program” regarding the hazards associated with structural steel erection.
Note: Authority cited: Section 142.3, Labor Code. Reference: Sections 142.3, 7252, 7253, 7254, 7258, 7261, 7262 and 7266, Labor Code.
1. Amendment of subsection (b) filed 5-3-78; effective thirtieth day thereafter (Register 78, No. 18). For prior history, see Register 76, No. 41.
2. Amendment of subsection (e)(1)(C) filed 5-12-83; effective thirtieth day thereafter (Register 83, No. 20).
3. Amendment filed 6-21-85; effective thirtieth day thereafter (Register 85, No. 25).
4. New subsections (i)-(i)(2) filed 12-15-93; operative 1-14-94 (Register 93, No. 51).
5. Amendment of subsections (g)(1), (g)(2), (g)(3)(A)-(B) and (g)(5) filed 4-23-98; operative 5-23-98 (Register 98, No. 17).
6. Amendment of subsections (g)(1)-(2) filed 7-2-98; operative 8-1-98 (Register 98, No. 27).
7. New subsection (a)(4) filed 7-25-2001; operative 8-24-2001 (Register 2001, No. 30).
8. Amendment of section heading, section and Note and new Appendices A and B filed 5-1-2002; operative 5-1-2002. Submitted to OAL for printing only pursuant to Labor Code section 142.3(a)(3) (Register 2002, No. 18).
9. Amendment of section and Appendix A heading and new Appendix C filed 7-3-2003; operative 8-2-2003 (Register 2003, No. 27).
10. Amendment of subsection (f)(1)(A) filed 3-15-2006; operative 4-14-2006 (Register 2006, No. 11).
11. Change without regulatory effect amending appendices A and B filed 5-19-2008 pursuant to section 100, title 1, California Code of Regulations (Register 2008, No. 21).
12. Amendment of subsection (k)(2) filed 6-6-2008; operative 7-6-2008. Submitted to OAL for printing only pursuant to Labor Code section 142.3(a)(3) (Register 2008, No. 23).
13. New subsections (l)(5)-(l)(5)(B) and redesignation of former subsection (l)(5) as new subsection (l)(5)(C) filed 8-27-2015; operative 8-27-2015. Submitted to OAL for printing only pursuant to Labor Code section 142.3(a)(3) (Register 2015, No. 35).