Cal. Code Regs. tit. 4, § 10092.8
(a) Timing of Submittal and Enrollment
(b) Complete Financing Submittal Requirements
(1) Documentation. A complete financing submittal must include the following documentation provided to the Authority by the Participating Contractor, Project Developer, and/or Finance Provider Entity:
(2) Data. A completed submittal includes the following data provided to the Authority in a format approved by the Authority:
Data Points
Data Must be Provided by One of These Parties:
Exceptions
Eligible Commercial Financing Customer Information
(A)
Customer name, e-mail address, and phone number
Contractor, Project Developer (PD), FPE
(B)
North American Industry Classification System (NAICS) Code applicable to the type of business
FPE
(C)
Method by which the customer qualifies as an Eligible Small Business Financing Customer pursuant to Section 10092.1(bb), or status as an Affordable Multifamily Customer
FPE
Not required for Microloans
(D)
The number of years in business
FPE
(E)
An indication of how the entity is organized, e.g., sole proprietorship, corporation, or LLC
FPE
Not required for Microloans
(F)
The customer's credit score
FPE
(G)
Credit scoring or reporting service relied upon to calculate the customer's credit score
FPE
(H)
The customer's annual revenue
FPE
Only for Eligible Financing Agreements greater than $350,000
(I)
Special business characteristics if known, e.g. woman-owned, veteran-owned, or minority-owned
FPE
(J)
Whether the customer owns the Eligible Property(ies) or is a tenant occupant
Contractor, PD, FPE
Property Information
(K)
Number of units or spaces at the Eligible Property for which EEMs were installed
Contractor, PD, FPE
Not required for Microloans
(L)
The street address, city, and ZIP code
Contractor, PD, FPE
(M)
Utility names and account numbers for all gas and electric providers at each Eligible Property, if applicable
Contractor, PD, FPE
For Microloans, name and account number for at least one utility
Project Information (for each contractor or Self-Installer's scope of work)
(N)
The method by which each EEM qualifies for the Program
Contractor, PD, FPE
(O)
The EEM category, e.g. “Lighting” or “Refrigeration”
Contractor, PD, FPE
(P)
The EEM measure name
Contractor, PD, FPE
(Q)
A brief description including size, energy performance, standard material descriptions, and/or specifications
Contractor, PD, FPE
Not required for Microloans
(R)
The quantity installed for each EEM
Contractor, PD, FPE
(S)
An indication of whether the EEM is replacing existing equipment or is a new installation
Contractor, PD, FPE
Not required for Microloans
(T)
An indication of whether the installation resulted in a fuel substitution for that measure
Contractor, PD, FPE
Not required for Microloans
(U)
The fuel for which there is expected energy impact as a result of installing the EEM
Contractor, PD, FPE
Not required for Microloans unless being repaid through OBR
(V)
Total cost of all EEMs installed as part of a Scope of Work
Contractor, PD, FPE
(W)
Total cost and brief description of improvements that were legally and practically required to complete a Scope of Work not accounted for in the total cost of EEMs, if applicable
Contractor, PD, FPE
(X)
Description of all Non-EEMs installed as part of a Scope of Work
Contractor, PD, FPE
Not required for Microloans
(Y)
Total cost of all Non-EEMs installed as part of a Scope of Work
Contractor, PD, FPE
(Z)
The Scope of Work Completion Date for any work performed by a Participating Contractor
Contractor
(AA)
Any fees charged by the Participating Project Developer and, if there are fees, a brief description of the services provided
PD
Not required for Microloans
(BB)
The amount of any Capitalized Interest included in the Total Financed Amount
FPE
Not required for Microloans
(CC)
An indication of whether the Participating Contractor or Eligible Commercial Financing Customer is seeking or has received a rebate or incentive from an IOU, REN, or CCA for a Scope of Work
Contractor, PD, FPE
(DD)
The amount of any utility, REN, or CCA rebate or incentive sought for a Scope of Work
Contractor, PD, FPE
Only for projects with rebates or incentives
Not required for Microloans
(EE)
The name of the utility, REN, or CCA issuing a rebate or incentive sought for a Scope of Work, the rebate or incentive name, and, if known, the project identification code
Contractor, PD, FPE
Only for projects with rebates or incentives
Not required for Microloans
(FF)
Date that the IOU, REN, or CCA approved the Eligible Commercial Financing Customer's custom measure(s), if applicable
Contractor, PD, FPE
Only for projects with a custom IOU, REN, or CCA incentive.
(GG)
A description of any Non-EEMs installed by contractors not enrolled with the Program or by Self-Installers
PD, FPE
Only for projects with installations by non-participating contractors
Not required for Microloans
(HH)
The total cost of any Non-EEMs installed by contractors not enrolled with the Program or by Self-Installers
PD, FPE
(II)
The name and CSLB number of the non-participating contractor company who installed Non-EEMs
PD, FPE
Only for projects with installations by non-participating contractors
Data Related to Measures Qualifying through the Professionally Certified Measure Method pursuant to Section 10092.7(b)(3). For each measure:
(JJ)
Whether the reported energy cost savings result from Energy Efficiency, Demand Response measures, or Distributed Generation
Energy Professional
(KK)
For Energy Efficiency and Demand Response: Energy Professional's estimate of the electric savings of each EE or DR measure certified by the Energy Professional. Savings must be reported in annual kWh for EE and peak kW for DR
Energy Professional
(LL)
For Energy Efficiency and Demand Response: Energy Professional's estimate of the gas savings of each EE or DR measure certified by the Energy Professional. Savings must be reported as annual therms for EE and peak therms for DR
Energy Professional
(MM)
The Energy Professional's name, business name, city, e-mail address, and phone number
Contractor, PD, FPE
(NN)
For Distributed Generation: Energy Professional's estimate of the annual energy generation or maximum energy capacity of storage. Energy must be reported in kWh, therms, or gallons
Energy Professional
(OO)
The Energy Professional's estimate of the annual greenhouse gas emissions avoided or reduced, in pounds of CO2 equivalent
Energy Professional
(PP)
An indication of whether the Energy Professional is a PE or CEM
Contractor, PD, FPE
(QQ)
The Energy Professional's certification ID or license number, as applicable
Contractor, PD, FPE
Financing Data
(RR)
The Finance Provider Entity's internal financing agreement number
FPE
(SS)
An indication as to whether the financing agreement is an Eligible Loan, Eligible Lease or Eligible Equipment Finance Agreement, Eligible Energy Service Agreement, or an Eligible Savings-Based Payment Agreement
FPE
(TT)
Total Financed Amount
FPE
(UU)
Whether a security interest was taken against the financing agreement, and, if so, an indication of the type of security interest taken
FPE
Not required for Microloans
(VV)
Date the financing agreement funded or is anticipated to fund
FPE
(WW)
Repayment term of the financing agreement and its maturity date or its contractual end date
FPE
(XX)
Interest rate applied to the financing agreement
FPE
Only for Loans, Leases and Equipment Financing Agreements
(YY)
Whether the interest rate is fixed or variable
FPE
Not required for Microloans
(ZZ)
Amount of the interest rate bought down by the contractor, if applicable
FPE
Only for Loans, Leases and Equipment Financing Agreements
Not required for Microloans
(AAA)
Monthly charges for ongoing service and maintenance related to the upkeep or performance of all installed measures
FPE
Only for Eligible Service Agreements and Eligible Savings-Based Payment Agreements
(BBB)
The interest rate the Eligible Commercial Financing Customer would have received without the benefit of the Loss Reserve
FPE
Only for Loans, Leases and Equipment Financing Agreements
Not required for Microloans
(3) Certifications. A completed financing submittal includes the following certifications provided to the Authority:
(A) Participating Contractor Certifications. Certification, signed by an individual authorized to legally bind the Participating Contractor, of the following:
(B) Project Developer Certification. Certification from an individual authorized to legally bind the Participating Project Developer of the following:
(C) Finance Provider Entity Certifications. Certification from the Primary Finance Provider Entity of the following:
(D) Eligible Commercial Financing Customer Certification. Certification, signed by an individual authorized to legally bind the Eligible Commercial Financing Customer of the following:
(E) Energy Professional Certification. The Energy Professional's certification, for each Eligible Energy Measure qualifying by the Professionally Certified Measure Method, as described in Section 10092.7(b)(3), of the following:
Note: Authority cited: Sections 26006 and 26009, Public Resources Code. Reference: Sections 26002, 26002.5, 26003, 26006, 26011 and 26040, Public Resources Code.
1. New section filed 12-17-2018 as a deemed emergency pursuant to Public Resources Code section 26009; operative 12-17-2018 (Register 2018, No. 51). A Certificate of Compliance must be transmitted to OAL by 6-17-2019 or emergency language will be repealed by operation of law on the following day.
2. Change without regulatory effect amending section filed 4-4-2019 pursuant to section 100, title 1, California Code of Regulations (Register 2019, No. 14).
3. New section refiled 6-11-2019 as a deemed emergency pursuant to Public Resources Code section 26009, including amendment of subsections (b)(1)(D), (b)(2)(D)(ii)e.-f., and (b)(2)(D)(iv)b., repealer of subsection (b)(2)(D)(vii)c., subsection relettering and amendment of Note; operative 6-18-2019 (Register 2019, No. 24). A Certificate of Compliance must be transmitted to OAL by 9-16-2019 or emergency language will be repealed by operation of law on the following day.
4. New section refiled 9-12-2019 as a deemed emergency pursuant to Public Resources Code section 26009; operative 9-16-2019 pursuant to Government Code section 11343.4(b)(2) (Register 2019, No. 37). A Certificate of Compliance must be transmitted to OAL by 12-16-2019 or emergency language will be repealed by operation of law on the following day.
5. Certificate of Compliance as to 9-12-2019 order, including further amendments, transmitted to OAL 12-13-2019 and filed 1-21-2020; amendments operative 1-21-2020 pursuant to Government Code section 11343.4(b)(3) (Register 2020, No. 4).
6. Amendment of section and Note filed 7-19-2021 as an emergency; operative 7-19-2021 (Register 2021, No. 30). A Certificate of Compliance must be transmitted to OAL by 1-18-2022 or emergency language will be repealed by operation of law on the following day.
7. Amendment of section and Note refiled 12-30-2021 as a deemed emergency pursuant to Public Resources Code section 26009; operative 1-18-2022 (Register 2021, No. 53). A Certificate of Compliance must be transmitted to OAL by 4-18-2022 or emergency language will be repealed by operation of law on the following day.
8. Amendment of section and Note refiled as a deemed emergency pursuant to Public Resources Code section 26009; operative 4-18-2022 (Register 2022, No. 15). A Certificate of Compliance must be transmitted to OAL by 7-18-2022 or emergency language shall be repealed by operation of law on the following day.
9. Certificate of Compliance as to 4-18-2022 order, including amendment of subsection (b)(2), transmitted to OAL 7-12-2022 and filed 8-15-2022; amendments effective 8-15-2022 pursuant to Government Code section 11343.4(b)(3) (Register 2022, No. 33).
10. Amendment filed 5-13-2024 as a deemed emergency pursuant to Public Resources Code section 26009; operative 5-13-2024 (Register 2024, No. 20). A Certificate of Compliance must be transmitted to OAL by 11-12-2024 or emergency language will be repealed by operation of law on the following day.
11. Amendment refiled 11-4-2024 as a deemed emergency pursuant to Public Resources Code section 26009; operative 11-13-2024 pursuant to Government Code section 11346.1(d) (Register 2024, No. 45). A Certificate of Compliance must be transmitted to OAL by 2-11-2025 or emergency language will be repealed by operation of law on the following day.
12. Amendment refiled 2-5-2025 as an emergency; operative 2-11-2025 pursuant to Government Code section 11346.1(d) (Register 2025, No. 6). A Certificate of Compliance must be transmitted to OAL by 5-12-2025 or emergency language will be repealed by operation of law on the following day.
13. Certificate of Compliance as to 2-5-2025 order transmitted to OAL 2-5-2025 and filed 3-20-2025 (Register 2025, No. 12).
14. Amendment of subsections (a)(2), (b)(2)(CC), (b)(2)(OO) and (b)(3)(E)(iv) filed 11-6-2025 as a deemed emergency pursuant to Public Resources Code section 26009; operative 11-6-2025 (Register 2025, No. 45). A Certificate of Compliance must be transmitted to OAL by 5-5-2026 or emergency language will be repealed by operation of law on the following day.
15. Amendment of subsections (a)(2), (b)(2)(CC), (b)(2)(OO) and (b)(3)(E)(iv) refiled 4-15-2026 as a deemed emergency pursuant to Public Resources Code section 26009; operative 5-5-2026 (Register 2026, No. 16). A Certificate of Compliance must be transmitted to OAL by 8-3-2026 or emergency language will be repealed by operation of law on the following day.