- (a) The person to whom a construction permit is issued shall request the inspection and all necessary re-inspections of that permitted construction project.
(b) Scheduled progress inspections are required for the following:
- (1) any underground or enclosed work prior to covering;
- (2) permanent buildings; and
- (3) accessory buildings or structures, or building components.
(c) The required progress inspections shall occur at the following stages of construction, when applicable:
- (1) Form inspection: When trenching is completed and forms have been set for the foundation, including all plumbing, mechanical, and electrical installations which may be concealed beneath the foundation or slab.
- (2) Frame inspection: When all structural framing is completed, including all electrical, mechanical, and plumbing installations which are to be enclosed within the walls.
- (3) Lath and/or wallboard inspection: When all lathing and/or wallboard interior and exterior is completed, but before any plaster is applied or before wallboard joints and fasteners are taped and finished.
- (4) Final inspection: When the permanent building, accessory building or structure, or building component, is completed.
Note: Authority cited: Section 18865, Health and Safety Code. Reference: Sections 18871.3, 18872, 18873.3 and 18873.4, Health and Safety Code.
History
1. New section filed 7-6-2004; operative 7-6-2004 pursuant to Government Code section 11343.4 (Register 2004, No. 28).
2. Amendment of subsection (a), new subsection (b), subsection relettering and amendment of newly designated subsection (c) filed 2-19-2013; operative 4-1-2013 (Register 2013, No. 8).