(a) The sponsor shall submit project progress reports to the Department that include the following:
- (1) Records of expenditures.
- (2) Description of project activities since the previous report.
- (3) Status of the project relative to the progress schedule.
- (4) Key issues that must be resolved.
- (5) Results of project monitoring.
- (b) The first progress report shall be made three months after contract award or upon submittal of the first invoice, whichever comes first.
- (c) Intermediate progress reports shall be made quarterly or upon reaching a milestone, whichever the contract requires.
(d) The sponsor shall submit a completion report that shall constitute the final progress report and must include:
- (1) All items required in Subsections (a)(1) through (a)(3).
- (2) Photographs of the before-project condition.
- (3) Photographs of planning and restoration activities and techniques.
- (4) Photographs of the completed condition.