(a) The department shall retain a consulting board:
- (1) To review the adequacy of the design of a dam and reservoir the department proposes to construct, or
- (2) To review the safety of the completed construction and the terms and conditions to be included in a certificate of approval for any dam owned by the department as issued, renewed or modified, no later than six months following any such action.
- (b) Where a board is retained to review the adequacy of the design of a dam and reservoir, it shall report its findings to the Director prior to the approval of an application to construct or enlarge the dam.
Note: Authority cited: Section 6078, Water Code. Reference: Section 6056, Water Code.
History
1. Renumbering and amendment of former Section 332 to Section 322 and renumbering and amendment of former Section 342 to Section 332 filed 8-4-83; effective thirtieth day thereafter (Register 83, No. 32). For prior history, see Register 77, No. 33.