(a) The following definitions apply to this section:
- (1) Access Ramps - “Access Ramps” mean those ramps that provide access to the levee crown from adjacent property and roads.
- (2) Patrol Roads - “Patrol Roads” means those roads that provide vehicular access along levee crowns and flood channels for inspection, maintenance, and flood fighting.
(b) Patrol roads must meet the following criteria:
- (1) Patrol roads must be surfaced with a minimum of four (4) inches of compacted, class 2 aggregate base (Caltrans Spec. 26-1.02A, July 1992) which is incorporated by reference, or equivalent.
- (2) Patrol road surfacing material must be compacted to a relative compaction of not less than ninety (90) percent per ASTM D1557-91, dated 1991, which is incorporated by reference with moisture content sufficient to obtain the required compaction.
- (3) Compaction tests by a certified soils laboratory may be required to verify compaction.
- (4) Paved patrol roads must meet the design requirements for paved bicycle trails, section 132.
(5) Levee crown surfacing must meet the following additional requirements:
- (A) Where the crown width is less than sixteen (16) feet, the minimum surfacing width must be ten (10) feet with a smoothly tapered transition to the edge of the levee shoulder.
- (B) Where the crown width is sixteen (16) feet or more, the minimum surfacing width must be twelve (12) feet with a two (2) foot-wide taper at each edge of the surfacing.
- (C) The crown roadway must be sloped a minimum of two- (2) percent.
- (6) Any patrol road which has been excavated or damaged must be restored to its original condition.
(c) Access ramps are of two common types, head-on or side approach, and must meet the following criteria:
- (1) Access ramps must be constructed of approved imported material.
- (2) The surfacing for all access ramps must be the same as for patrol roads. Subdivisions (b)(1), (b)(2) and (b)(3) of this section also apply to access ramps.
- (3) Any excavation made in a levee section to key the ramp to the levee must be backfilled in four- (4) to six- (6) inch layers with approved material and compacted to a relative compaction of not less than ninety (90) percent per ASTM D1557-91, dated 1991, and above optimum moisture content.
- (4) Compaction tests by a certified soils laboratory may be required to verify compaction.
- (5) All access ramps must be constructed in such a manner so as to direct all surface drainage away from the levee section.
- (6) Approved gates must be installed across access ramps at locations where vehicular access by the public is possible.
- (7) Side approach ramps must be used on the waterside levee slope.
- (8) Side approach ramps on the waterward slope of the levee must slope downstream.
- (9) Typical plans for each type of approach ramp with restrictions and requirements are shown on Figures 8.08 and 8.09.
Note: Authority cited: Section 8571, Water Code. Reference: Sections 8608 and 8710, Water Code.
History
1. New section and figures 8.08 and 8.09 filed 9-30-96; operative 10-30-96 (Register 96, No. 40).