(a) The board shall act upon applications within the following time limits:
- (1) When the board is the lead agency pursuant to CEQA and an environmental impact report is prepared, it shall approve or disapprove a project within six months from the date of the certification of the environmental impact report.
- (2) When the board is the lead agency and a negative declaration is adopted or if the project is exempt from CEQA, the board shall approve or disapprove a project within three months from the date of the adoption of the negative declaration.
(3) When the board is a responsible agency for a project that has been approved by the lead agency, it shall either approve or disapprove the project within whichever is the longer:
- (A) Within one-hundred-eighty (180) calendar days of the date on which the lead agency has approved the project; or
- (B) Within one-hundred-eighty (180) calendar days of the date on which the application is deemed complete.
- (b) Applicants may waive the requirement that applications be acted upon within such periods. Waivers must be in writing or expressed on the record at a hearing.
Note: Authority cited: Section 8571, Water Code. Reference: Sections 65950 and 65952, Government Code; and Section 8730.1, Water Code.
History
1. New section filed 9-30-96; operative 10-30-96 (Register 96, No. 40).
2. Amendment of subsections (a)(3)(A)-(B) filed 2-15-2012; operative 2-15-2012 pursuant to Government Code section 11343.4 (Register 2012, No. 7).