(a) A School District may request a modernization supplemental grant to construct a new or expand an existing multipurpose, gymnasium, library, school kitchen, or a hybrid combination of any of these four facility types, including, but not limited to, multipurpose/gymnasium hybrid, multipurpose/school kitchen hybrid, or multipurpose/gymnasium/school kitchen, when all of the following are met:
- (1) The site does not have an existing Minimum Essential Facility, or the existing Minimum Essential Facility is not adequate to serve the enrollment of the school. For the purposes of this Section, to determine if an existing Minimum Essential Facility is inadequate, the existing Square Footage is 60 percent or less than the square footage necessary for the enrollment in the current CBEDS Report at the time of receipt of an Approved Application at the site as calculated pursuant to the chart in Section 1859.82.1(b)(4)(B)2.
- (2) The site has not previously received funding pursuant to this article to construct or expand a Minimum Essential Facility.
(3) An Approved Application for Modernization funding has been received by OPSC for a project wherein the DSA-approved plans contain the construction or expansion of a Minimum Essential Facility eligible for this grant.
- (A) An Approved Application received by the OPSC, on or after October 31, 2024, may be amended to request this supplemental grant provided the plans and specifications that contain the expansion or construction of a Minimum Essential Facility eligible for this supplemental grant were approved by the DSA prior to the receipt of the Approved Application.
- (B) If the School District wishes to amend its Approved Application to include a request for this supplemental grant and the plans and specifications were approved by DSA after the receipt of the Approved Application, the School District must request in writing that the Approved Application be withdrawn and removed from OPSC's workload list. The resubmitted Approved Application will receive a new received date by OPSC.
- (4) The construction contract(s) for the construction or expansion of the Minimum Essential Facility was executed on or after July 3, 2024.
- (5) The Minimum Essential Facility must meet the requirements pursuant to the California Code of Regulations, Title 5.
- (6) For purposes of this Section, a multipurpose/gymnasium Hybrid is considered to be both a multipurpose and a gymnasium. A school site with a middle school and/or high school pupils is eligible for one multipurpose and one gymnasium; therefore, if a school site has an adequate multipurpose and an adequate gymnasium, it is not eligible for a Multipurpose/Gymnasium Hybrid under this Section.
(b) If all conditions in Subsection (a) are met, and the site is lacking one or more of the Minimum Essential Facilities, the application is eligible to receive a supplemental grant based on the Square Footage of the new Minimum Essential Facility constructed justified by enrollment at the project site as follows:
- (1) Determine the current enrollment at the site using the CBEDS Report at the time of receipt of an Approved Application.
- (2) The eligible Square Footage for the Minimum Essential Facility shall be the lesser of the actual Square Footage constructed or the Square Footage justified by enrollment pursuant to the chart in Section 1859.82.1(b)(4)(B)2.
- (3) If a School District submits documentation that demonstrates additional toilet space must be constructed to obtain plan approval from DSA, the eligible toilet Square Footage may be increased by the amount of Square Footage required to obtain plan approval.
- (4) Beginning September 8, 2025, the permanent Square Footage amount(s) determined in (b)(2) above shall be multiplied by $312 per square foot for all non-Toilet Facilities and by $559 for Toilet Facilities (includes shower/locker area and physical therapy area for individuals with Exceptional Needs). The amounts shown will be adjusted in the manner prescribed in Section 1859.71.
- (5) Beginning September 8, 2025, the portable Square Footage amount(s) determined in (b)(2) above shall be multiplied by $69 per square foot for all non-Toilet Facilities and by $181 for Toilet Facilities (includes shower/locker area and physical therapy area for individuals with Exceptional Needs). The amounts shown will be adjusted in the manner prescribed in Section 1859.71.
- (6) In addition to the funding provided in Subsections (4) and (5), an amount equal to 35 percent of the sum of Subsections (4) and (5) for costs associated with site development, demolition, landscaping and other costs incurred when adding a Minimum Essential Facility to a site, utility costs, utility connections and other related fees necessary for the Minimum Essential Facility.
- (7) In lieu of 35 percent funding provided in (6) above, the School District has the option of requesting 60 percent of eligible costs contained within Section 1859.76(a), (b), and (c) by submitting a detailed cost estimate for requests related to site development work for the eligible Square Footage in the qualifying Minimum Essential Facility and any justification documents that will support the work must be submitted with the Form SAB 50-04. The Board will approve reasonable and appropriate site development work that meets common engineering practices and industry standards that are consistent with the specific site conditions if the site development costs are consistent with the most current edition of the Current Construction Costs publication by the Sierra West Group. The design professional must certify to the district that the site development work does not exceed the minimum requirements to develop the site to meet educational needs and/or standards. This amount will be prorated for any excess Square Footage constructed beyond the eligible Square Footage determined in (b)(2) and (b)(3).
(c) If all conditions in Subsection (a) are met, and the site's existing Minimum Essential Facility is not adequate to serve the enrollment of the school, the application is eligible to receive a supplemental grant based on the square footage of the expanded Minimum Essential Facility constructed justified by enrollment at the project site as follows:
- (1) Determine the current enrollment at the site using the CBEDS Report at the time of receipt of an Approved Application.
- (2) The eligible Square Footage for the Minimum Essential Facility shall be the lesser of the delta between the Square Footage of the existing Minimum Essential Facility and actual Square Footage constructed or the delta between the Square Footage of the existing Minimum Essential Facility and the Square Footage justified by enrollment pursuant to the chart in Section 1859.82.1(b)(4)(B)2.
- (3) If a School District submits documentation that demonstrates that additional toilet space must be constructed to obtain plan approval from DSA, the eligible toilet Square Footage may be increased by the amount of Square Footage required to obtain plan approval.
- (4) Beginning September 8, 2025, the permanent Square Footage amount(s) determined in (b)(2) above shall be multiplied by $312 per square foot for all non-Toilet Facilities and by $559 for Toilet Facilities (includes shower/locker area and physical therapy area for individuals with Exceptional Needs). The amounts shown will be adjusted in the manner prescribed in Section 1859.71.
- (5) Beginning September 8, 2025, the portable Square Footage amount(s) determined in (b)(2) above shall be multiplied by $69 per square foot for all non-Toilet Facilities and by $181 for Toilet Facilities (includes shower/locker area and physical therapy area for individuals with Exceptional Needs). The amounts shown will be adjusted in the manner prescribed in Section 1859.71.
- (6) In addition to the funding provided in Subsections (4) and (5), an amount equal to 35 percent of the sum of Subsections (4) and (5) for costs associated with site development, demolition, landscaping and other costs incurred when adding a Minimum Essential Facility to a site, utility costs, utility connections and other related fees necessary for the Minimum Essential Facility.
- (7) In lieu of 35 percent funding provided in (6) above, the School District has the option of requesting 60 percent of eligible site development costs contained within Section 1859.76(a), (b) and (c) by submitting a detailed cost estimate for requests related to site development work for the eligible Square Footage in the qualifying Minimum Essential Facility and any justification documents that will support the work must be submitted with the Form SAB 50-04. The Board will approve reasonable and appropriate site development work that meets common engineering practices and industry standards that are consistent with the specific site conditions if the site development costs are consistent with the most current edition of the Current Construction Costs publication by the Sierra West Group. The design professional must certify to the School District that the site development work does not exceed the minimum requirements to develop the site to meet educational needs and/or standards. This amount will be prorated for any excess Square Footage constructed beyond the eligible Square Footage determined in (c)(2) and (c)(3).
In addition to any other funding authorized by these Regulations, the Board shall provide grant amounts identified in subsections (b) or (c) for an application for modernization if the eligible project includes a Minimum Essential Facility pursuant to Education Code Section 17073.16. The School District must meet all requirements to qualify for Modernization funding, prior to the additional grant pursuant to this section.
Note: Authority cited: Sections 17070.35 and 17073.16, Education Code. Reference: Sections 17073.16 and 17074.25, Education Code.
History
1. New section filed 9-8-2025 as an emergency; operative 9-8-2025 (Register 2025, No. 37). A Certificate of Compliance must be transmitted to OAL by 3-9-2026 or emergency language will be repealed by operation of law on the following day.
2. Certificate of Compliance as to 9-8-2025 order transmitted to OAL 3-3-2026 and filed 4-15-2026 (Register 2026, No. 16).