- (a) Within 15 business days following the date of the inclusion letter, the enforcement agency must issue a compliance schedule to the operator of the facility pursuant to PRC 44106(a). Within 5 business days of issuance of the compliance schedule, a copy will be sent to the board.
- (b) The compliance schedule must have the final compliance date within one year from the date of the inclusion letter. The enforcement agency may issue a compliance schedule for more than one year but not to exceed two years, after informing the executive director in writing. A one-year extension beyond two years may be made prior to the expiration of the two-year period upon approval by the executive director. The executive director shall report any such approvals or disapprovals to the Board.
Note: Authority cited: Sections 40502 and 43020, Public Resources Code. Reference: Section 44106, Public Resources Code.
History
1. New section filed 3-5-2003; operative 4-4-2003 (Register 2003, No. 10).