E. Notwithstanding any other law:
F. For job-order-contracting construction services only:
2. If the contractor subcontracts or intends to subcontract part or all of the work under a job order and if the job-order-contracting construction services contract includes descriptions of standard individual tasks, standard unit prices for standard individual tasks and pricing of job orders based on the number of units of standard individual tasks in the job order:
(a) The contractor has a duty to deliver promptly to each subcontractor invited to bid a coefficient to the contractor to do all or part of the work under one or more job orders:
(b) If not previously delivered to the subcontractor, the contractor has a duty to deliver promptly the following to each subcontractor invited to or that has agreed to do any of the work included in any job order:
G. Notwithstanding any contrary provision of this section or this title, a purchasing agency shall not:
J. The following provisions apply to all construction services procured under section 41-2535, 41-2536, 41-2537, 41-2578 or 41-2579:
2. The following requirements apply to the construction work to be performed by subcontractors and do not apply to construction work that the purchasing agency and the contractor agree in writing will be self-performed by the contractor:
(b) The purchasing agency shall include in each contract: