Ariz. Rev. Stat. § 34-223
A. Every claimant who has furnished labor or material in the prosecution of the work provided for in a contract for which a payment bond is furnished under section 34-222, and who has not been paid in full for the labor or material for the work before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by the claimant or material was furnished or supplied by the claimant for which the claim is made, shall have the right to sue on the payment bond for the amount, or the balance of the amount, unpaid at the time of institution of the suit and to prosecute the action to final judgment for the sum or sums justly due the claimant, and have execution thereon, provided however that any claimant who has a direct contractual relationship with a subcontractor of the contractor furnishing the payment bond but not a contractual relationship express or implied with the contractor has a right of action on the payment bond on giving the contractor the following notices: