Ariz. Rev. Stat. § 32-1182
B. A construction contract may provide for a billing cycle other than a thirty day billing cycle if the construction contract specifically sets forth such other billing cycle and either of the following applies:
1. The following legend or substantially similar language setting forth the other billing cycle appears in clear and conspicuous type on each page of the plans, including bid plans and construction plans:
Notice of Alternate Billing Cycle
This contract allows the owner to require the submission of billings or estimates in billing cycles other than thirty days. Billings or estimates for this contract shall be submitted as follows:
______________________________________________________________
______________________________________________________________
______________________________________________________________
2. The following legend or substantially similar language setting forth the other billing cycle appears in clear and conspicuous type on each page of the plans, including bid plans and construction plans:
Notice of Alternate Billing Cycle
This contract allows the owner to require the submission of billings or estimates in billing cycles other than thirty days. A written description of such other billing cycle applicable to the project is available from the owner or the owner's designated agent at (telephone number or address, or both), and the owner or its designated agent shall provide this written description on request.
C. An owner may make progress payments, release of retention and final payment later than seven days after the date the billing or estimate is certified and approved if both:
2. The following legend or substantially similar language setting forth the specified number of days appears in clear and conspicuous type on each page of the plans, including bid plans and construction plans:
Notice of Extended Payment Provision
This contract allows the owner to make payment within _____ days after certification and approval of billings and estimates for progress payments, within _______ days after certification and approval of billings and estimates for release of retention and within ____ days after certification and approval of billings and estimates for final payment.
D. Except as provided in subsection F of this section, a billing or estimate for a progress payment shall be deemed certified and approved fourteen days after the owner receives the billing or estimate, unless before that time the owner or the owner's agent prepares and issues a written statement stating in reasonable detail the owner's reasons for not certifying or approving all or a portion of the billing or estimate. The owner is deemed to have received the billing or estimate when the billing or estimate is submitted to any person designated by the owner for receipt or for certification and approval of the billing or estimate. The owner may withhold from a progress payment a reasonable amount for retention. An owner may decline to certify and approve a billing or estimate or portion of a billing or estimate for any of the following reasons:
F. An owner may extend the period within which the billing or estimate for progress payments, release of retention and final payment is certified and approved if both:
2. The following legend or substantially similar language, setting forth the specified number of days, appears in clear and conspicuous type on each page of the plans, including bid plans and construction plans:
Notice of Extended Certification and
Approval Period Provision
This contract allows the owner to certify and approve billings and estimates for progress payments within ____ days after the billings and estimates are received from the contractor, for release of retention within ____ days after the billings and estimates are received from the contractor and for final payment within ____ days after the billings and estimates are received from the contractor.
H. On substantial completion of the work, a contractor shall submit a billing or estimate for release of retention. Except as provided in subsection F of this section, the billing or estimate for release of retention shall be deemed certified and approved within fourteen days after the owner receives the billing or estimate, unless before that time the owner or the owner's agent issues a written statement stating in reasonable detail the owner's reasons for not certifying or approving all or a portion of the billing or estimate. The owner is deemed to have received the billing or estimate when the billing or estimate is submitted to any person designated by the owner for receipt or for certification and approval of the billing or estimate. The owner may:
K. On final completion of the work, a contractor shall submit a billing or estimate for final payment. Except as provided in subsection F of this section, a billing or estimate for final payment shall be deemed certified and approved fourteen days after the owner receives the billing or estimate, unless before that time the owner or owner's agent prepares and issues a written statement stating in reasonable detail the reasons the billing or estimate has not been certified or approved. The owner is deemed to have received the billing or estimate for final payment when the billing or estimate is submitted to any person designated by the owner for receipt of or for certification and approval of the billing or estimate. The owner may:
U. Notwithstanding anything to the contrary in this section, an owner may define "retention", "substantial completion" and "final completion" to have meanings different than those stated in section 32-1181, if:
V. Notwithstanding anything to the contrary in this section, an owner may establish different timing and conditions for when the contractor may submit a billing or estimate for release of retention or for final payment and for when such payments shall be due, if:
W. The legend for making one or more of the modifications set forth in subsections U and V of this section shall be as follows:
Notice of Alternate Arrangements for
Release of Retention and Final Payment
This contract allows the owner to make alternate arrangements for the occurrence of substantial completion, the release of retention and making of final payment. Such alternate arrangements are disclosed on sheet no. _____ of these plans.