Ariz. Rev. Stat. § 28-7366
A. The department may procure the following services pursuant to this section:
C. In the procurement of construction services pursuant to this section:
1. The department shall issue a request for qualifications for each contract and publish notice of the request for qualifications in the same manner as provided in section 28-6923. The request for qualifications shall:
2. For each request for qualifications, the department shall initiate a selection team pursuant to section 28-7365, subsection B. A person who is a member of a selection team shall not be a contractor under the contract or provide construction, construction services, materials or services under the contract. The selection team shall:
(c) After any interviews or if interviews are not held, in order of preference, based on the criteria and the weighting of criteria established and published by the department and included in the request for qualifications, select a final list for the contract of persons or firms the selection team deems to be the most qualified to provide the construction services and, in the case of a contract that will be negotiated under subsection E of this section, rank the persons or firms on the final list in order of preference. The selection team shall base the selection of the final list and the order of preference on demonstrated competence and qualifications only. The number of persons or firms on the final list shall be the number of persons or firms specified in the request for qualifications, except that:
D. The department shall award a contract for construction services to one of the persons or firms on the final list prepared pursuant to subsection C of this section as provided in subsection E or F of this section, except that, if fewer than the number of persons or firms on the final list respond to the request for proposals pursuant to subsection F of this section but at least two persons or firms on the final list submit responsive proposals, or if one or more of the persons or firms on the final list drop out of the selection process pursuant to subsection E or F of this section:
E. For the single contract included in the request for qualifications, the department shall enter into negotiations for the contract with the highest qualified person or firm on the final list for the construction services. The negotiations shall include consideration of compensation and other contract terms that the department determines to be fair and reasonable to the department. In making this decision, the department shall take into account the estimated value, the scope, the complexity and the nature of the construction services to be rendered. If the department is not able to negotiate a satisfactory contract with the highest qualified person or firm on the final list at compensation and on other contract terms the department determines to be fair and reasonable, the department shall formally terminate negotiations with that person or firm. The department may undertake negotiations with the next most qualified person or firm on the final list in sequence until an agreement is reached or a determination is made to reject all persons or firms on the final list. If a contract for construction services is entered into pursuant to this subsection:
F. As an alternative to subsection E of this section, the department may award job-order-contracting construction services as follows:
3. For job-order-contracting construction services, the request for proposals shall include:
I. Notwithstanding any other law:
J. For job-order-contracting construction services only:
2. If the contractor subcontracts or intends to subcontract any of the work under a job order and if the job-order-construction services contract includes descriptions of standard individual tasks, standard unit prices for standard individual tasks and pricing of job orders based on the number of units of standard individual tasks in the job order:
(a) The contractor has a duty to deliver promptly to each subcontractor invited to bid a coefficient to the contractor to do all or part of the work under one or more job orders:
(b) If not previously delivered to the subcontractor, the contractor has a duty to deliver promptly the following to each subcontractor invited to or that has agreed to do any of the work included in any job order: