Ariz. Admin. Code § R18-14-104
| Discharge or Influent per Day under the Individual APP or Notice of Disposal (in Gallons) | Annual Registration Fee | Annual Registration Fee if New Facility Under New APP Not Yet Constructed |
| 3,000 to 9,999 | $714 | $357 |
| 10,000 to 99,999 | $1,427 | $357 |
| 100,000 to 999,999 | $3,568 | $714 |
| 1,000,000 to 9,999,999 | $8,562 | $892 |
| 10,000,000 or more | $12,130 | $1,070 |
| Permit Type | Annual Fee | Annual Fee if New Facility Under New AZPDES Not Yet Constructed |
| Municipal separate storm sewer system | $14,270 | N/A |
| Wastewater treatment plant (based on gallons of discharge per day): | ||
| § Less than 99,999 | $357 | $357 |
| § 100,000 to 999,999 | $714 | $714 |
| § 1,000,000 to 9,999,999 | $3,568 | $892 |
| § 10,000,000 or more | $5,708 | $1,070 |
| Facility or activity that is not a wastewater treatment plant or municipal separate storm sewer and designated in the permit as either: | ||
| Major | $3,568 | $892 |
| Minor | $714 | $714 |
| Pretreatment program | $4,281 | N/A |
| Consolidated individual permit for multiple AZPDES individual permits, as allowed under A.A.C. R18-9-B901(C) | Aggregate of the applicable annual fees of each individual permit | Aggregate of the applicable annual fees of each individual permit |
| Permit Type | Annual Registration Fee | Annual Waste Disposal Fee |
| Area | $10,000 (and not subject to any other annual registration fee in Tables 3.1 and 3.2) | N/A |
| Class I | No Annual Registration Fee | $0.002/gallon. Minimum Fee: $10,000/year Maximum Fee: $25,000/year |
| Class II | See Table 3.2 | N/A |
| Class III | See Table 3.2 | N/A |
| Class V “Individual” | See Table 3.2 | N/A |
| Class VI | No Annual Registration Fee | $0.08/ton Minimum Fee: $10,000/year |
| Design Injection Flow Rate in Gallons per day1, 2 | Annual Registration Fee |
| 3,000 to 9,999 | $600 |
| 10,000 to 99,999 | $1,200 |
| 100,000 to 999,999 | $3,000 |
| 1,000,000 to 9,999,999 | $7,000 |
| 10,000,000 or more | $10,000 |
1 A Class II, III or V Individual UIC permittee with multiple wells or multiple permits may consolidate their same-class wells for the purpose of “design injection flow rate in gallons per day” under Table 3.2.
2 An Area permit is not subject to Table 3.2.
Schedule A. Repealed
Schedule A adopted effective November 15, 1996 (Supp. 96-4). Schedule repealed by final rulemaking at 7 A.A.R. 564, effective January 2, 2001 (Supp. 01-1).
Schedule B. Repealed
Schedule B adopted effective November 15, 1996 (Supp. 96-4). Schedule repealed by final rulemaking at 7 A.A.R. 564, effective January 2, 2001 (Supp. 01-1).
Schedule C. Repealed
Schedule C adopted effective November 15, 1996 (Supp. 96-4). Schedule repealed by final rulemaking at 7 A.A.R. 564, effective January 2, 2001 (Supp. 01-1).
Schedule D. Repealed
Schedule D adopted effective November 15, 1996 (Supp. 96-4). Schedule repealed by final rulemaking at 7 A.A.R. 564, effective January 2, 2001 (Supp. 01-1).
Adopted effective November 15, 1996 (Supp. 96-4). Amended by final rulemaking at 7 A.A.R. 564, effective January 2, 2001 (Supp. 01-1). Amended by final rulemaking at 17 A.A.R. 568, effective July 1, 2011 (Supp. 11-2). Tables 2 and 3 removed from this Section to conform with the A.A.C. codification scheme; amended by final rulemaking at 28 A.A.R. 1811 (July 29, 2022), effective September 6, 2022 (Supp. 22-3). Amended by final rulemaking at 29 A.A.R. 1869 (August 25, 2023), with an immediate effective date of August 4, 2023 (Supp. 23-3). Amended by final rulemaking at 31 A.A.R. 1161 (April 4, 2025), with an immediate effective date of March 4, 2025 (Supp. 25-1).