(1) The applicant has sixty (60) days from the issuance of the certificate of need in which to file a preapplication for a solid waste landfill or transfer station permit with the Division of Environmental Quality.
(2) If a preapplication is not filed within such sixty-day period, the certificate of need shall expire.
(b)
(1) The applicant has six (6) months from the issuance of the certificate of need in which to file an application for a solid waste landfill or transfer station permit with the division.
(2) If such application is not filed within such six-month period, the certificate of need shall expire.
(c) A certificate of need shall be issued to a specific person or entity.
(d) Under no conditions or circumstances shall a certificate of need be assigned or otherwise transferred to any person or entity other than the one originally specified on the certificate of need.