(a) Within thirty (30) days of receipt of the initial application, the Benton County Regional Solid Waste Management District will determine if the application:
- (1) Is administratively complete; and
(2) Contains all required:
- (A) Information;
- (B) Documents; and
- (C) Submittals.
- (b) Any additional information the district determines is necessary to make a decision on the need of the proposed facility will be requested within this time.
- (c) If additional information is requested by the district, it will again determine completeness of the application within thirty (30) days of the receipt of the additional information.