27 CAR pt. 92, Appendix D
EXAMPLE OF RISK ALLOCATION MATRIX 1 of 4
| RISK | Design-Bid-Build | Change | Design-Build | |||
|---|---|---|---|---|---|---|
| Agency | Shared | Contractor | Agency | Design-Builder | ||
| Design Issues | ||||||
| Definition of Scope | X | X | ||||
| Project Definition | X | X | ||||
| Establishing Performance Requirement | X | X | ||||
| Preliminary Survey/Base Map | X | X | ||||
| Geotechnical Investigation - Initial Borings based on Preliminary Design | X | X | ||||
| Geotechnical Investigation- Borings based on Final Design | X | ➡ | X | |||
| Establish/Define Initial Subsurface Conditions | X | X | ||||
| Initial Project Geotechnical Analysis/Report based on Preliminary Design | X | X | ||||
| Final Project Geotechnical Analysis/Report based on Final Design | X | ➡ | X | |||
| Plan Conformance with Regulations/Guidelines/RFP | X | ➡ | X | |||
| Plan Accuracy | X | ➡ | X | |||
| Project Design Criteria | X | X | ||||
| Conformance to Project Design Criteria | X | ➡ | X | |||
| Design Review Process | X | ➡ | X | |||
| Design QC | X | ➡ | X | |||
| Design QA | X | ➡ | X | |||
| Owner Review Time | X | X | ||||
| Changes in Scope | X | X | ||||
| Constructability of Design | X | X | ||||
| Contaminated Materials | X | X |
EXAMPLE OF RISK ALLOCATION MATRIX 2 of 4
| RISK | Design-Bid-Build | Change | Design-Build | |||
|---|---|---|---|---|---|---|
| Agency | Shared | Contractor | Agency | Design-Builder | ||
| Construction | ||||||
| DBE Compliance | X | X | ||||
| Safety/Safety QA | X | X | ||||
| Construction Quality/Workmanship | X | X | ||||
| Schedule | X | X | ||||
| Materials Quality | X | X | ||||
| Materials Documentation | X | X | ||||
| Material Availability | X | X | ||||
| Initial Performance Requirements of QA Plan | X | X | ||||
| Final Construction/Materials QC/QA Plan | X | ➔ | X | |||
| Construction/Materials QA | X | ➔ | X | |||
| Construction QC | X | X | ||||
| Construction QA Procedural Compliance Auditing | X | ➔ | X | |||
| Construction IA Testing/Inspection | X | X | ||||
| Construction Staking | X | ➔ | X | |||
| Erosion Control | X | ➔ | X | |||
| Spill Prevention | X | ➔ | X | |||
| Accidents within Work Zone/Liability | X | X | ||||
| Third Party Damages | X | X | ||||
| Operations and Maintenance During Construction | X | X | ||||
| Maintenance under Construction - New Features | X | X | ||||
| Maintenance under Construction - Existing Features | X | X | ||||
| Maintenance of Traffic | X | ➔ | X | |||
| Quantity/Cost of WSP Callbacks | X | ➔ | X | |||
| Availability of WSP Callbacks | X | X | ||||
| Damage to Utilities under Construction | X | X | ||||
| Falsework | X | X | ||||
| Shop Drawings | X | X | ||||
| Equipment Failure/Breakdown | X | X | ||||
| Work Methods | X | X | ||||
| Early Start of Construction/At Risk Construction | X | ➔ | X | |||
| Community Relations | X | X | ||||
| Performance of Defined Mitigation Measures | X | ➔ | X | |||
| Warranty | X | ➔ | X |
EXAMPLE OF RISK ALLOCATION MATRIX 3 of 4
| RISK | Design-Bid-Build | Change | Design-Build | |||
|---|---|---|---|---|---|---|
| Agency | Shared | Contractor | Agency | Design-Builder | ||
| Force Majeure/Acts of God | ||||||
| Strikes/Labor Disputes - On Site Labor | X | ➡ | X | |||
| Tornado/Earthquake | X | X | ||||
| Epidemic, Terrorism, Rebellion, War, Riot, Sabotage | X | X | ||||
| Archaeological or Paleontological Discovery * | X | X | ||||
| Suspension of any Environmental Approval * | X | X | ||||
| Changes in Law | X | X | ||||
| Lawsuit Against Project | X | X | ||||
| Storm/Flooding | X | X | ||||
| Fire or Other Physical Damage | X | X | ||||
| * Note: Will ultimately rollover to Environmental | ||||||
| Differing Site Conditions/Changed Conditions | ||||||
| Changed Conditions | X | X | ||||
| Differing Site Conditions | X | X | ||||
| Completion and Warranty | ||||||
| Establishment/Definition of any Risk Pool | X | X | ||||
| Long-Term Ownership/Final Responsibility | X | X | ||||
| Insurance | X | X |
EXAMPLE OF RISK ALLOCATION MATRIX 4 of 4
| RISK | Design-Bid-Build | Change | Design-Build | |||
|---|---|---|---|---|---|---|
| Agency | Shared | Contractor | Agency | Design-Builder | ||
| Local Agency, Utility, Railroad Issues | ||||||
| Identification of Initial Local Agency Impacts | X | X | ||||
| Obtaining Initial Local Agency Permits | X | X | ||||
| Establishing Initial Local Agency Requirements | X | X | ||||
| Establishing Final/Actual Local Agency Impacts | X | ➔ | X | |||
| Modifications to Existing Local Agency Permits | X | ➔ | X | |||
| Identification of Initial Utility Impacts from Preliminary Design | X | X | ||||
| Establish Initial Utility Locations/Conditions | X | X | ||||
| Defining required Utility Relocations from Preliminary Design | X | X | ||||
| Utility Relocations prior to Contract Execution | X | X | ||||
| Relocation of Utilities under Project Utility Agreement during Contract | X | X | ||||
| Modified Project Utility Agreement with Private Utility based on Final Design | X | ➔ | X | |||
| Modified Project Utility Agreement with Public Utility based on Final Design | X | ➔ | X | |||
| Damage to Public or Private Utilities under Construction | X | X | ||||
| Verification of Utility Locations/Conditions | X | ➔ | X | |||
| Coordination with Utility Relocation Efforts during Contract | X | ➔ | X | |||
| Unforeseen Delays due to Utility/Third Party | X | X | ||||
| Utility/Third Party Delays resulting from Contract Final Design | X | ➔ | X | |||
| Identification of RR Impacts based on Preliminary Design | X | X | ||||
| Obtaining Initial RR Agreement based on Preliminary Design | X | X | ||||
| Coordinating with RR under Agreement | X | ➔ | X | |||
| Other Work/Coordination | X | ➔ | X | |||
| Third Party Agreements (Fed, Local, Private, etc.) | X | X | ||||
| Coordinating with Third Parties under Agreement | X | ➔ | X | |||
| Coordination/Collection for Third Party Betterments | X | ➔ | X | |||
| Coordination with Other Projects | X | ➔ | X | |||
| Coordination with Adjacent Property Owners | X | ➔ | X |