(a)
- (1) Reappraisal plans will specify the exact order in which townships will be reviewed during Phase 1 of the reappraisal.
- (2) An alternative will allow the reappraisal plan to appraise all cities in a county first, and then appraise all noncity properties in township order.
- (3) Regardless of which plan is utilized, appraisers will be required to meet or exceed the monthly production tables established in the reappraisal plan.
(b)
- (1) Reappraisal plans will specify expected progress by township or city and number of parcels planned for each month during Phase 1 of the reappraisal.
- (2) A breakdown by city or township-range is not required for Phase 2 of the planned progress report.
(3)
- (A) However, a projected total per month is required.
- (B) For these purposes, “month” is defined as the twentieth of the preceding month through the nineteenth of the current month.
- (c) An approved planned progress report may require revision if it is discovered at any time before or during the reappraisal that the plan does not conform to requirements of the Assessment Coordination Division’s rules.
Codification Notes: This section as promulgated prior to codification into the Code of Arkansas Rules provided as follows: "Adopted 10/1/99 Amended 03/03/02 Amended 04/26/10"