(a) If any construction authorized by a CCN or a CECPN is not started within four (4) months from the date of the certificate, the utility shall file a statement stating:
- (1) Why the construction was not started; and
- (2) When it will be started.
(b)
- (1) Within thirty (30) days after booking of the final expenses of the construction authorized by any CCN or CECPN or by such other time that may be fixed by Arkansas Public Service Commission order, the utility shall file a report showing the date the requested construction was completed.
(2) The report shall include a:
- (A) Map showing changes, if any, from the application for the certificate; and
- (B) Detailed statement of the estimated costs of the construction and the final costs of the construction by major cost category.
- (3) The report shall reference the docket number in which the certificate was granted.
Codification Notes: This section was promulgated as Rule 6.05 of the Rules of Practice and Procedure prior to codification in the Code of Arkansas Rules. "CCN" means a certificate of public convenience and necessity. "CECPN" means a certificate of environmental compatibility and public need.