- (a) The Construction Section has contract oversight and responsibility.
(b)
- (1) The design professional shall provide the Construction Section current approved-for-construction plans and specifications.
- (2) The plans will be in half size.
- (3) A copy of the plans and specifications that the GMP is established on will be provided to the Construction Section, the Design Review Section, department official, and contractor, and the plans and specifications will be stamped or noted as “Guaranteed Maximum Price” and “Approved for Construction” with the date and signature or seal of the design professional.
- (4) For additional design professional requirements, see 22 CAR § 111-1707.
(c) Phased fast track projects.
- (1) A notice to proceed will be issued to the contractor for each approved-for-construction phase of the work.
- (2) No work may commence on any phase of work without Building Authority Division approval.
Codification Notes: "GMP" means guaranteed maximum price.