- (a) Requests for payments from capital improvement funds shall be made using a payment document using the general accounting procedures pursuant to Arkansas Administrative Statewide Information System.
(b)
- (1) Each payment document shall indicate the Building Authority Division project number and be supported by the design professional’s certification of the contractor’s estimates.
- (2) Estimates must be broken down by units of work normally used to calculate the work accomplished during the invoicing period.
(c)
- (1) The design professional shall conduct site visits to determine the responsibility and performance required by the contract documents.
- (2) Refer to 22 CAR § 111-1606 for design professional’s project observation requirements.
- (3) Observations shall concur with the contractor’s payment request and shall be submitted in written form with the pay request.
(d)
- (1) Observation reports by design professionals are required once a month at a minimum.
- (2) The use of the standard AIA Document G-711 "Architect Field Report" or other approved form is acceptable.
- (3) Reports are to be maintained on file by the design professional and shall be provided to the owner/department and the Construction Section monthly.
(4) Minimal observation reports shall include, but are not limited to the following phases of construction:
- (A) Foundation;
- (B) Roof deck;
- (C) Roofing and insulation;
- (D) Mechanical equipment installation;
- (E) Electrical equipment installation;
- (F) Prior to installation of interior wall, backfilling trenches, laying concrete, and ceiling finishes concealing the work, i.e., plumbing, electrical, and HVACR, shall be observed; and
- (G) Plumbing equipment and fixtures installation.
(e)
- (1) Contractor final pay requests must be approved by the design professional.
- (2) Payment requests shall be submitted by the contractor in one (1) original.
Codification Notes: "HVACR" means heating, ventilation, air conditioning, and refrigeration.